The backward pass is a technique used in project management to determine the latest possible start and finish times for project activities without delaying the overall project schedule. By analyzing the network diagram, the backward pass helps identify which tasks can be delayed and how much flexibility exists within the project timeline. This process is crucial for managing critical paths and ensuring that all project deadlines are met while optimizing resource allocation.